JiuJu Automation focuses on the intelligent upgrading of the whole process of speakers, integrating the four core technologies of visual inspection, precision assembly, AI quality inspection and data traceability to provide customized solutions for TWS headphones, car audio, multimedia smart audio speakers, etc., and achieve production capacity increase of 300%+, yield rate of 99.8%, and reduce the comprehensive cost of 60%, completely solving the pain points of the industry, such as manual dependence, stable quality control and delivery cycle. dependence, unstable quality control, long delivery cycle and other industry pain points. Based on the product characteristics and production scenarios of speakers, it creates a full-process automation system from the entry of raw materials to the release of finished products from the warehouse, covering the three major categories of micro, small and medium-sized, and adapting to the needs of multi-specification and multi-batch production.
Q: What do I need to pay attention to in the installation and commissioning of speaker automation equipment? How to ensure the correct installation and normal operation of the equipment?
A: The installation and commissioning of speaker automation equipment is a key link to ensure the normal operation of the equipment, need to pay attention to the following matters: Installation site requirements: 1. The site should be dry and well-ventilated, avoiding humid and dusty environments. 2. The floor should be level, firm and capable of supporting the weight of the equipment. 3. Adequate operating and maintenance space shall be provided around the equipment. 4. It should be kept away from sources of strong magnetic field interference, such as large motors and transformers.
Power supply configuration requirements: 1. The power supply voltage should meet the requirements of the equipment, usually AC220V or AC380V. 2. The capacity of the power supply shall meet the maximum power requirements of the equipment and avoid voltage fluctuations. 3. Dedicated power switches and protection devices shall be provided. 4. The grounding wire shall be reliably connected to ensure the safety of equipment and personnel.
Safety and security measures: 1. Installation of safety warning signs to remind attention to safe operation. 2. Installation of safety barriers or nets to prevent persons from accidentally entering hazardous areas. 3. Installation of an emergency stop device to ensure rapid shutdown in case of emergency.
Debugging Points: 1. No-load debugging: in the case of not placing the workpiece, test whether the various functions of the equipment is normal. 2. Load commissioning: production tests using standard workpieces to adjust equipment parameters. 3. Performance testing: testing the positioning accuracy, repeatability, production beat and other performance indicators of the equipment. 4. Safety test: Test the safety protection devices for proper functioning.
Installation and commissioning should be carried out by professional and technical personnel to ensure operational safety and commissioning quality. After the commissioning is completed, operators should be trained to familiarize themselves with the operation of the equipment and safety precautions.
Core view:
Core point: Speaker automation equipment installation and commissioning need to pay attention to site requirements, power supply configuration, safety protection and commissioning points. Professional installation and commissioning and operator training is the key to ensure the normal operation of the equipment.
JiuJi Automation Advantage:
Frequently Asked Questions FAQ
Click a question to expand the answer
01What must the customer prepare before the equipment arrives?
Prepare along four lines: power (capacity, circuits, earthing), air (pressure, flow, dryness), floor (load capacity, levelness, vibration isolation) and space (entry route, operating and maintenance clearance).If any one of the four is not in place, the equipment cannot be started even after it arrives and the whole schedule slips. We recommend issuing a site-readiness checklist as soon as the contract is signed rather than confirming it just before dispatch.
02What are the power requirements?
380 V three-phase as standard, 220 V for some dedicated machines, with voltage stabilisation and a dedicated circuit breaker.Magnetizers are pulsed high-current loads: give them a dedicated circuit with adequate breaker capacity and do not share a feed with precision inspection equipment. Total line power is calculated from the actual configuration and stated at the proposal stage, not estimated from experience.
03What are the compressed-air requirements?
0.5 to 0.8 MPa, with dried air provided at the site.Stations with pneumatic grippers and vacuum nozzles are sensitive to moisture and oil: condensate clogs nozzles and slows cylinder response, showing up as intermittent dropped parts. Size the dryer and filters to actual air consumption; this is not the item to economise on.
04What should be checked about floor loading?
Riveting and press-type machines are heavy; slab load capacity and vibration isolation must be confirmed in advance, especially for upper-floor workshops.Levelness matters as well: long lines are sensitive to floor level differences, and excessive variation deforms the frame and shifts locating accuracy. Local reinforcement or isolation pads may be needed; retrofitting afterwards is expensive.
05Are there temperature and humidity requirements?
Micro-speaker assembly is sensitive to static and dust, so a clean, ESD-protected environment is recommended. Dispensing is more sensitive still, because adhesive viscosity varies with temperature and directly affects the volume dispensed.If the workshop has no temperature and humidity control, say so at the proposal stage so that compensation can be designed into the equipment or the process window adjusted.
06What should be checked on the entry route in advance?
Three points: door width and height, turning radius along the route, and lift car dimensions and rated load.Line equipment ships in sections, and section dimensions are marked on the layout drawing; check the route against the largest section envelope. Narrow factory doors and small goods lifts are common blockers, and modifying them costs far more than planning ahead.
07How many stages does installation and commissioning involve?
Four: positioning and levelling, electrical and pneumatic connection, powered trial running of individual machines, and linked commissioning of the whole line.The first two are the foundation; if they are done badly everything after is re-adjusted. The third verifies machine motions and safety interlocks; only the fourth addresses cycle time and interlock logic. Skip any step and it comes back as rework.
08What does the customer need to provide during commissioning?
Three things: incoming material to the real specification (samples cannot stand in for production stock), the team leaders who will actually run the equipment taking part, and a clear acceptance standard with a named decision-maker.The second is the one most often overlooked: if the operators are not involved in commissioning, they will adjust parameters to their own habits once production starts and undo the validated window.
09How long does commissioning take?
Typically 45 to 120 calendar days for a complete line, across seven stages from requirements review to volume validation; manufacturing and in-house debugging account for the largest share.On-site installation and commissioning is one of those stages, and its duration is confirmed by the number of sections and process complexity. A single machine follows the sample trial route, with a trial period of 3 to 10 working days.
10How should acceptance be organised?
Around four metrics: cycle-time attainment, yield, OEE and changeover time, with the contract stating how each is measured, how many samples are used and who decides.Volume validation should be a continuous 72-hour assessment covering changeovers and fault handling. Signing off after a small batch under ideal conditions is hard to revisit later.
11How should operator training be organised?
In three tiers: operators (loading, changeover, alarm handling), maintenance (daily checks, consumable replacement, air and adhesive circuit care) and supervisors (dashboards and traceability queries).Training must take place at real production pace, hands-on. A single demonstration during commissioning guarantees operating errors once production begins.
12What are the common causes of rework?
Four: floor level differences deforming the frame, moisture in the air supply slowing pneumatic components, incoming material differing from the trial sample, and voltage fluctuation causing locating drift.None of these lies within the machine itself, yet they are most often blamed on the equipment. The site-readiness checklist exists to eliminate them in advance.
Jiuju Automation is an SRDI “Little Giant” Enterprise and has specialised in speaker automated assembly for 16 years, serving more than 2,500 customers. The company holds 256 technical patents and operates a 10,000 m² production base, offering one-stop solutions from standalone equipment to complete automated lines. Jiuju speaker automated assembly lines use high-precision vision positioning (±0.01 mm), AI-based inspection and fast changeover (<25 minutes), raising production efficiency by 300%+ and achieving a product yield of 99.8% with a 60% reduction in overall cost.